- 01Theta targets first gold in Mar Qtr 2027, subject to approvals
- 02TGME plant 81% complete; 110,000t ore stockpiled
- 03A$109.6m bond drawn; cash of A$96.2m
Theta Gold Mines (ASX: TGM) is targeting its first gold pour in the March quarter of 2027 as construction of its Transvaal Gold Mining Estates (TGME) project in South Africa approaches completion.
Executive chair Bill Guy outlined progress at the annual general meeting in Sydney on 27 November, with construction of the gold processing plant 81% complete and development expenditure estimated at A$84.8 million (US$56m) to the end of October.
The company has completed two drawdowns under its Nordic bond financing and has stockpiled 110,000 tonnes of ore in preparation for plant commissioning.
Theta Gold holds a 74% interest in the project in Mpumalanga province, where its revised feasibility study completed in February outlined a 13.1-year operating life.
Bond Funding Support
The A$136.4m (US$90m) senior secured bond issue Theta completed in June provides funding for project development over a four-year term at an annual coupon rate of 12.75%, with interest payable quarterly in advance.
Theta completed the second drawdown on 25 November, taking total proceeds released under the facility to A$109.6m (US$72.6m), with further releases dependent on construction funding requirements and cost-to-complete tests.
The company reported an existing cash balance of approximately A$96.2m (US$63.52m) at 25 November, with an undrawn bond balance of A$20.8m (US$13.7m).
The remaining facility includes a provision for cost overruns subject to approval by independent technical engineer Behre Dolbear Australia, which monitors the project build.
Processing Plant Advancing
The first shipment of 17 containers of crushing and screening equipment has arrived on-site, with a second shipment of 14 containers expected by 18 December to support installation of the three-stage circuit.
Theta has contracted the supply of two ball mills, with the twin-mill configuration designed to improve operational flexibility and allow maintenance without relying on a single mill.
The gold room is nearing completion, while gold casting equipment is already on-site and a furnace has been purchased for smelting and refining the metal ahead of the production start-up.
A new Siton underground drill rig has also arrived to support mechanised mine development ahead of production from underground workings.
The project schedule targets dry commissioning in the December quarter and completion of commissioning in the March quarter, with the timing of first gold subject to outstanding regulatory approvals.
Staged Underground Mining Plan
The development plan calls for initial production from existing rock dumps and tailings while Theta Gold undertakes an 18-month pre-development period at the Beta mine before extracting ore from its underground stopes.
Mining at Rietfontein is scheduled to start in the December quarter of 2028, followed by a planned increase in production from the Clewer-Dukes Hill-Morgenzon and Frankfort mines.
The February feasibility study forecasts recovery of 871,000 ounces of gold over the planned operating life at an average recovered grade of 4.28 grams per tonne, with peak annual production of approximately 115,000oz.
Theta has identified 43 historical gold mines across its holdings, with only four included in the current mine plan and approximately 3,000,000oz of gold resources outside that plan.